Gantt chart from a task list

Turn a list of jobs with start days and lengths into a Gantt chart, one bar per job, so you can see what overlaps.

Advanced · 10 min · 11 steps

In this lesson

  • A Gantt chart draws each job as a bar that starts on its start day and is as long as the job takes.
  • Build it from a stacked bar chart of the job names, the start days and the lengths in days.
  • Leave the finish day out of the chart. The chart puts the length after the start by itself.

Try a free lesson first

Why your formula broke when you copied it

Lock a cell with $ so a formula keeps working when you copy it down.

Beginner · 7 min · Free, with no sign-up

Do the free lesson on your computer.

Send yourself the link and open it on a laptop or desktop.

On your computer, go tolearnford.com/go/GX5R

This lesson is in the full Excel course

US$149 once

Tax included. New lessons are added as they're written.

Get the full course, US$149

30-day money-back guarantee if you've opened fewer than 10 paid lessons.

  • All 217 Excel lessons open today, and every new one as it's written.
  • The Roadmap, Skills and all eight paths.
  • A cheat sheet for every lesson you finish.

Already have the course? Sign in

Skill
Charts
Stage
Advanced

Where it sits in Charts 14 lessons

The steps

11 steps: 3 explanations, 6 Do this, 2 questions, then Your turn.

Try a free lesson first

Why your formula broke when you copied it

Lock a cell with $ so a formula keeps working when you copy it down.

Beginner · 7 min · Free, with no sign-up

Do the free lesson on your computer.

Send yourself the link and open it on a laptop or desktop.

On your computer, go tolearnford.com/go/GX5R